Project information: Construction of a six-story, 170,000-square-foot corporate headquarters with offices, a data center, a bank branch, cafeteria and fitness center.
Cost: $55 million
Start date: July 2008
Expected completion date: Early 2010
Construction manager: LeChase Construction Services LLC
Architect: LaBella Associates P.C.

Owner: St. John Fisher College
Location: Pittsford
Project information: Construction of the Joseph S. Skalny Welcome Center, a 17,500-square-foot building with offices, an art gallery and conference center.
Cost: $3.75 million
Start date: June 2008
Expected completion date: Summer 2009
Construction manager: LeChase Construction Services LLC
Architect: LaBella Associates P.C.

Owner: Town of Farmington
Location: Farmington
Project information: Expansion of the wastewater treatment plant, including a new influent structure.
Cost: $18 million
Start date: September 2004
Expected completion date: September 2008
General contractor: Crane Hogan Structural Systems Inc.
Architect: MRB Group Engineering, Architecture, Surveying P.C.
HVAC and mechanical contractors: Lawman Heating and Cooling Inc.
Electrical contractor: Blackmon-Farrell Electric Inc. and M.W. Controls Service Inc.

Owner: North Forest Office Providers
Location: 421 Penbrooke Drive, Penfield
Project information: Construction of a single-story brick office building with more than 18,000 square feet of professional and medical office space.
Cost: $1.8 million
Start date: May 2008
Expected completion date: May 2009
General contractor: North Forest Office Providers

Owner: North Forest Office Providers
Location: 1120 Crosspointe Drive, Webster
Project information: Construction of a single-story brick office building with nearly 13,000 square feet of professional and medical office space.
Cost: $1.28 million
Start date: August 2008
Expected completion date: August 2009
General contractor: North Forest Office Providers

Owner: North Forest Office Providers
Location: 250 Lucius Gordon Drive, West Henrietta
Project information: Construction of a single-story brick office building with 13,000 square feet of professional and medical office space.
Cost: $1.3 million
Start date: January 2008
Expected completion date: November 2008
General contractor: North Forest Office Providers

Owner: North Forest Office Providers
Location: 95 Canal Landing Blvd.
Project information: Construction of a single-story brick office building with more than 18,000 square feet of professional and medical office space.
Cost: $1.8 million
Start date: July 2008
Expected completion date: February 2009
General contractor: North Forest Office Providers

Owner: Tim Horton’s Restaurant
Location: 2037 W. Ridge Road
Project information: Construction of a 3,000-square-foot restaurant.
Cost: $800,000
Start date: August 2008
Expected completion date: October 2008
Developer: Simonetti Properties and Management LLC

Owner: North Forest Office Providers
Location: 99 Canal Landing Blvd.
Project information: Construction of a single-story brick office building with 13,000 square feet of professional and medical office space.
Cost: $1.3 million
Start date: June 2008
Expected completion date: January 2009
General contractor: North Forest Office Providers

Owner: North Forest Office Providers
Location: 125 Sully’s Trail, Pittsford
Project information: Construction of a single-story brick office building with more than 10,000 square feet of professional and medical office space.
Cost: $1.02 million
Start date: June 2008
Expected completion date: May 2009
General contractor: North Forest Office Providers

Owner: Simonetti Properties and Management LLC
Location: 2081 W. Ridge Road
Project information: Construction of a 27,500-square-foot medical and professional building.
Cost: $2.2 million
Start date: May 2008
Expected completion date: March 2009
General contractor: Simonetti General Contractors Inc.
Architect: Torchia Structural Engineering and Design P.C.
Electrical contractor: Daniel Simonetti

Owner: Getinge USA LLC
Location: 1777 E. Henrietta Road
Project information: Renovation of existing, 9,200-square-foot office and display space for a new boardroom and new showroom.
Cost: $900,000
Start date: March 2008
Expected completion date: August 2008
Construction manager: Holdsworth Klimowski Construction LLC
Architect: Gardner Plus Architects PLLC
Electrical contractor: Q-Tech Engineering P.C.

09/05/2008 (C) Rochester Business Journal