Owner: University of Rochester
Location: Wilson Quadrangle, River Campus
Project information: Construction of Raymond F. LeChase Hall, a four-story, 65,000-square-foot facility with 14 classrooms and a three-story atrium.
Cost: $24 million
Start date: May 2011
Expected completion date: January 2013
Construction manager: LeChase Construction Services LLC
Architect: Bergmann Associates P.C. and SHW Group

Owner: University of Rochester
Location: Rochester
Project information: Vertical expansion of the James P. Wilmot Cancer Center with addition of three floors.
Cost: $42 million
Start date: December 2010
Expected completion date: August 2012
Construction manager: The Pike Co. Inc.

Owner: Your Local Pharmacy LLC
Location: 780 Joseph Ave.
Project information: Construction of a 2,400-square-foot community pharmacy.
Cost: $400,000
Start date: August 2011
Expected completion date: October 2011
General contractor: Martini Construction Inc.
Architect: Pardi Partnership Architects P.C.

Owner: Monarch Senior Living
Location: Webster
Project information: Construction of a 45-bed, low-income senior housing project.
Cost: $5.8 million
Start date: March 2011
Expected completion date: January 2012
Construction manager: Lecesse Construction Co.
General contractor: Lecesse Construction Co.
Architect: SWBR Architects & Engineers P.C.
HVAC and mechanical contractors: M/E Engineering P.C.

Owner: East House Corp.
Location: 435 State St.
Project information: Conversion of a vacant parking garage into 45 one-bedroom apartments with support spaces and 4,700 square feet of office and community space.
Cost: $8.6 million
Start date: June 2011
Expected completion date: April 2012
General contractor: Buckingham General Contractors and Capstone Construction Co. Inc.
Architect: Pardi Partnership Architects P.C.

Owner: Lyons Central School District
Location: 10 Clyde Road, Lyons
Project information: Renovation and reconstruction of the elementary school, middle/high school and transportation building to improve technology and conserve energy.
Cost: $1.6 million
Start date: September 2010
Expected completion date: September 2011
General contractor: Massa Construction Inc.
Architect: Mossien Associates Architects P.C.
HVAC and mechanical contractors: Cogenic Mechanical
Electrical contractor: Kaplan-Schmidt Electric Inc.

Owner: Monroe Community College
Location: Building 9, East Henrietta Road
Project information: 80,000-square-foot renovation of science building with modern classrooms and labs.
Cost: $10 million
Start date: June 2010
Expected completion date: December 2011
Construction manager: DiMarco Constructors
General contractor: Pepe Construction Co. Inc.
Architect: SWBR Architects & Engineers P.C.
HVAC and mechanical contractors: M/E Engineering P.C.

Owner: St. John’s Home
Location: Penfield
Project information: Construction of two 8,000-square-foot Green House homes serving 10 residents each.
Cost: $3.7 million
Start date: August 2011
Expected completion date: October 2011
Construction manager: Pride Mark Homes
Architect: SWBR Architects & Engineers P.C.
HVAC and mechanical contractors: Mech Tech HVAC Inc., American Plumbing Inc. and Callea Electric Inc.

9/16/11 (c) 2011 Rochester Business Journal. To obtain permission to reprint this article, call 585-546-8303 or e-mail rbj@rbj.net.

x

Check Also

Workers prepare ingredients to be used for a variety of recipes on the menu at Real Eats. (Photo by Diana Louise Carter)

Real Eats simplifies meal preparation (access required)

  With so many choices for meal and delivery services, it can be hard to stand out in a crowded ...

roc2change_1

Student summit addresses diversity, racism (access required)

When Khuram Hussain was 7 years old he came to school to find a cupcake and an American flag on ...